PJM's capacity auction falls 6.8 GW short as data-centre load outruns new power
The largest US grid cleared at its price cap for a third year and missed its reliability target again. Without the cap, prices would have been 70% higher.
Key figures
- 6.8 GW
- Shortfall vs reliability requirement
- $325
- Clearing price per MW-day (at cap)
- $554.72
- Simulated price without cap
The constraint on AI build-out that matters most in the United States may no longer be chips. On July 14, PJM Interconnection, which runs the grid and wholesale market for 13 states and Washington, DC, including the data-centre corridor of northern Virginia, published the results of its capacity auction for the 2028/29 delivery year. For the second year running, the market failed to procure enough capacity to meet PJM's own reliability standard.
What happened
The auction cleared 138,318 MW of unforced capacity, and utilities using the fixed-resource alternative committed another 10,864 MW, for a total of 149,182 MW. That is 6,831 MW below the RTO reliability requirement, a shortfall almost identical to the 6,516 MW gap in the previous auction. The resulting installed reserve margin is 14.4%, against the 20% PJM considers necessary to keep the risk of losing load to one day in ten years.
| Delivery year | RTO clearing price ($/MW-day) | Note |
|---|---|---|
| 2024/25 | $28.92 | Pre-AI-boom baseline |
| 2025/26 | $269.92 | First large jump |
| 2026/27 | $329.17 | At cap |
| 2027/28 | $333.44 | At cap; 6,516 MW short |
| 2028/29 | $325.00 | At cap; 6,831 MW short |
Every zone cleared at the $325 cap. PJM's own simulation shows what the cap is suppressing: without it, the auction would have cleared at about $554.72 per MW-day, with Commonwealth Edison's zone in northern Illinois at $776.69, and the total value of cleared capacity would have risen by $13.3 billion to about $29.7 billion.
Why it matters
The arithmetic is driven by demand. PJM raised its reliability requirement to 156,013 MW from 152,400 MW, with the forecast load increase attributed largely to additional large loads, the category dominated by data centres. Supply barely moved: total offered capacity rose by about 3,400 MW, mostly from accounting changes in accredited capacity and fewer unoffered megawatts, and only 524.7 MW of genuinely new generation and uprates cleared.
The region also failed PJM's market-structure test, meaning a small number of suppliers could be pivotal, so market-power mitigation was applied to all existing generation. In plain terms, the market is tight enough that sellers have leverage, and a price cap is the main thing holding bills down.
PJM stressed that a shortfall does not mean it will be unable to serve load, but that it would operate with slimmer reserves and greater risk. Its tariff requires a reliability backstop procurement if three consecutive auctions clear more than one percentage point below the target reserve margin; with two now on the books, PJM says it is working with stakeholders on backstop and large-load rules.
Perspectives
For AI infrastructure investors, the auction is a reminder that power is now the scarcest input. Hyperscalers increasingly sign their own deals for generation, including nuclear restarts, gas plants and on-site power, precisely because grid capacity cannot be assumed. Developers with secured interconnection and power become more valuable; projects without it face delays that no amount of GPU supply can fix.
For households and state regulators, the issue is cost allocation. Capacity costs flow through to retail bills, and the cap has kept prices around $325 for three straight auctions only by leaving reliability targets unmet. Politicians in PJM states have increasingly argued that data centres should pay a larger share of the grid upgrades and new supply their load requires.
For grid sceptics of the AI boom, the numbers cut both ways. Load forecasts have repeatedly been revised up on data-centre requests, some of which may be speculative or duplicated across sites. If AI demand falls short, the shortfall could ease on its own; if it materialises, the gap between demand and buildable supply will widen.
What to watch
- PJM's proposals for a reliability backstop procurement and rules for connecting large loads, and how costs would be assigned.
- Whether the price cap and floor are extended beyond the current transitional auctions.
- Bilateral power contracts between hyperscalers and generators, which could reduce the need for backstop procurement.
- Revisions to PJM's large-load forecast as data-centre projects firm up or fall away.
Researched and drafted with AI assistance under editorial review. Report errors to support@aiseeker.dev.
Sources
This report synthesises the sources below. Primary sources are marked.